CALL TO ORDER – The meeting of the Rockefeller Township Board of Supervisors was
called to order at 6:00 p.m. at the Township Municipal Building by Chairman, Julie Powell.
PRESENT – Present were Julie Powell, Chairman; Skyler Herb, Vice-Chairman (via phone);
John Jackson, Supervisor; and Stephanie McKinney, Administrator; Visitors- Paula Greco, Ron
Gay, Grace Herrold, George Herrold, Colin Clayberger, Brad Zeigler, Larry Willard, and Robert
Tegge.
APPROVAL OF MINUTES – John made a motion to approve the minutes. Skyler seconded the
motion. Motion passed without opposition.
TREASURER’S REPORT – Skyler made a motion to approve the Treasurer’s report and file
for audit. John seconded the motion. Motion carried without opposition.
CORRESPONDENCE -Penn DOT Municipal Outreach Program – April 14th Noon – 2:00;
DEP Sewage Planning Approval for Kent & Heather Nunamaker; Penn DOT Bridge Inspection
Notification.
SPECIAL INTEREST –
PUBLIC COMMENTS (Agenda Items)
PLANNING COMMISSION REPORT – Planning Commission met March 2 and approved
and signed a subdivision for the Wynn Estate. John made a motion seconded by Julie to approve
and sign the subdivision for the Wynn estate. Motion was passed unanimously.
UNFINISHED BUSINESS
Road Status Report – Larry reported that the road crew was trimming trees and will soon sweep
the roads.
2026 Road Projects – Julie moved, seconded by John to approve the approximate numbers for
the 2026 road projects and submit them to the COG. Seal coat single application is 107,827 SY
and double coat 2,800 SY. Motion was passed unanimously. Larry will draft a list of roads to
visit for the road review.
Zoning Investigations – A nuisance property was discussed and a complaint form will be
completed before any action is taken.
Tyler Karycki/Bill Yost – Julie has not talked with DEP and hopes to talk to them soon.
Page 2 Township Meeting 03-10-26
Clemens Road Bridge – No Report.
Data Center Ordinance- Solicitor Karpowich will draft an ordinance for review.
Pivot Solar Agreement – The agreement was approved but it was determined that the township
would not see any money until the project is completed and earning an income.
Possible New Building – The new storage building was placed on hold until funds are received
from the Pivot Solar agreement. Larry asked about moving the propane tank and prepping the
site. Moving the tank will cost $1,000 for the concrete and the cost to move the piping, plus we
need a suitable place to move it to. Costs will be estimated for moving the propane tank and
prepping the site with stone.
Clemens Road Bridge- No report.
Tressler Road Drainage Issue – This will be reviewed again during road review.
Sunbury Fire Dept Agreement – Julie reported that the board had a very informative discussion
with Sunbury Fire Company and have decided to keep them as the township primary provider.
Planning Commission Member – A member is still needed for the Planning Commission.
Watershed Committee Member – Lynn is unable to be on the committee at this time. Julie has
a couple of people in mind to ask.
Part-Time Snow Plow Driver – No report.
Tree Removal- Concerning the tree removal at the corner of Seven Points and Airport Roads a
letter was sent to the owners and the owners have started to clean up the trees.
Sale of Kubota Tractor – Skyler moved, seconded by John to approve the sale of the old
Kubota tractor and flail mower on Municibid as two separate pieces. Motion was passed
unanimously. Larry suggested we use the money from this sale to purchase a generator for the
church for their emergency shelter.
Road Crew Computer – Julie moved, seconded by Skyler to purchase a computer for the road
crew with a cost not to exceed $1,000.00. Motion was passed unanimously.
EMC Dividend Check – A dividend check was received from EMC Insurance to $2,348.14.
Fire Escrow – A fire escrow check was received for Lauren Rhoads whose barn that burned
down on SR 890. Once the barn is demolished and removed Ed Wenger will check the site to
verify removal before the check is released.
Page 3 Township Meeting 03-10-26
NEW BUSINESS
Public Comment – Paula recommended that the township keep using Light-Heigel. Julie noted
that Curtis is not retiring yet, as was reported previously.
Review of and authorization to pay all bills – John made a motion to pay all the bills. Julie
seconded the motion. Motion passed without opposition.
Motion to Adjourn – John made a motion to adjourn the meeting at 6:40 p.m. Skyler seconded
the motion. Motion passed without opposition.
CENTRAL PENN BANK General Fund $282,091.16
CENTRAL PENN BANK Escrow Account $3,200.34
CENTRAL PENN BANK Liquid Fuels $80,911.25
EQUIPMENT FUND 80,488.18
Respectfully Submitted,
Stephanie A. McKinney
Administrator